Repairs to the Huntsville Annex’s parking lot are coming, but at almost twice the original budget.
Crews will fix drainage by adding a new catch basin and re-pave the lot, which currently services the Huntsville Public Library and a medical clinic.
Tulloch Engineering will do the work at a cost of $116,000, up from the original budget of $60,000. “We did only receive one bid for the project, and as we’re seeing this year it’s extremely high construction prices,” said Engineering Technologist Brandon Hall.
Hall noted that there is a $10,000 contingency fund for any further cost overflows, and town staff are in discussions on how to better prepare for increased construction costs in the future.
Huntsville Council approved the project with the cost increase on Monday, to be funded through the town’s Capital Replacement Reserve. The work is expected to be done by July 31.