The Pines’ generator upgrade coming in over budget

The Pines Long Term Care Home will get a new emergency generator, but it will cost more than double what was budgeted.

According to a report to the district’s Health Services Committee on Thursday, the current 150 kilowatt generator can only power essential heating, lighting, care systems, and equipment, which “limits the level of care and services” during an outage.

Bob MacGregor, Capital Project Coordinator with the district, told committee the new 400 kilowatt generator would solve that problem.

“This upgrade will ensure the entire home is powered and [can] continue to operate normally in the event of a Hydro outage,” said MacGregor.

Committee voted to amend the district’s 2022 budget with another $392,702 for the project, for a total of $731,002. The bulk of the additional funds, $338,300, come from the federal government’s Investing in Canada Infrastructure Program.

According to MacGregor, the increase largely comes from building an outdoor enclosure for the larger generator, rather than housing it in the same space as the current one.

“Through the design process, it was determined that the new generator needed to be housed in a larger, self-contained enclosure outside the building,” said MacGregor. “This is the significant component to the required budget amendment included in this recommendation.”

The contract for acquiring and installing the new generator was awarded to Sutherland-Schultz, the only bid out of the four the district received that included the enclosure.

The delivery date is set for just over a year from now, which MacGregor said came as a surprise. He noted that the contractor said they might be able to shorten that by up to 20 weeks, depending on their supplier.

Continue Reading

cfbk Now playing play

cfbg Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Scott Aitchison officially resigns his seat in the House of Commons

Scott Aitchison has officially resigned from his seat in the House of Commons following the Nov. 26 parliamentary sitting.

Planned hydro outage scheduled in Gravenhurst on Nov. 29

Hydro One has scheduled a planned power outage in Gravenhurst to carry out maintenance work on Nov. 29.

Town of Bracebridge to hold annual Holiday Market on Nov. 28

The Town of Bracebridge is hosting its annual Holiday Market on Nov. 28 at the Muskoka Lumber Community Centre.

Three Huntsville residents charged following drug trafficking investigation

Police say three Huntsville residents were arrested and charged with two counts of possession of a Schedule I substance for the purpose of trafficking and possession of proceeds of property obtained by crime.

Two Gravenhurst residents charged following theft at Bracebridge grocery store

Two Gravenhurst residents have been charged following a shoplifting incident at a grocery store on Muskoka Road 118 in Bracebridge.
- Advertisement -