King William reconstruction project advances in Huntsville

Work continues on the King William reconstruction project in downtown Huntsville, with crews preparing for the next phase of infrastructure upgrades.

Throughout this week (June 22 to 26), officials said crews will test a temporary water system and begin transferring water services to it, as well as prepare for upcoming underground pipe replacement work by digging access pits and locating underground utilities along the corridor.

Last week, construction crews completed excavation, subgrade and compaction work, while continuing efforts to identify underground services. A temporary water pipe was installed along part of King William Street to help maintain water service during construction. Sections of curb, asphalt, sidewalk, and landscaping were removed to make way for underground work, and crews began rebuilding the road base on the northbound side of the street. Temporary traffic signals were also installed at the Rogers Cove Drive intersection.

The Town says businesses within the construction zone remain open and accessible to customers. One lane of traffic remains available in each direction, although motorists should expect delays and allow extra travel time.

Officials are also advising that temporary water service interruptions are expected in the coming weeks. Advance notice will be provided before any planned disruptions.

Hilary Hilton
Hilary Hilton
Hilary Hilton is a news reporter based in Muskoka with a strong passion for storytelling. She brings seven years of experience to her reporting, including three years in newspaper journalism and four years as a magazine editor and writer at the University of Toronto, where she studied English Language and Literature. After spending two years living in the UK and traveling abroad, she is elated to be back in her home country. Hilary is driven by a love of writing and a belief in the power of local news to connect and strengthen communities. To share a story, email hhilton@vistaradio.ca

Continue Reading

cfbk Now playing play

cfbg Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Moose FM Thanksgiving Radiothons raises over $467,000 for Muskoka hospital foundations

After 12 hours on air, Huntsville’s 105.5 Moose FM raised $350,554 for the Huntsville Hospital Foundation (HHF), while Bracebridge’s 99.5 Moose FM raised $116,734 for the South Muskoka Hospital Foundation (SMHF).

Five individuals charged in relation to recreational shooting in Georgian Bay Township

Officers have been proactively conducting patrols of areas the public voiced concern about with respect to recreational shooting.

C. difficile outbreak declared at South Muskoka Memorial Hospital

A C. difficile outbreak has been declared on the North Wing at the Bracebridge hospital.

Sever thunderstorm warning issued for Muskoka region

A severe thunderstorm warning is now in effect for the Huntsville-Baysville region.

Bracebridge’s Manna Food Bank to deliver 200 Thanksgiving hampers

The Manna Food Bank in Bracebridge is delivering 200 Thanksgiving hampers to residents throughout the community on Oct. 9.
- Advertisement -