King William Street in Huntsville to undergo reconstruction this spring

The District of Muskoka will be upgrading the underground infrastructure along King William Street in Huntsville this spring.

According to officials, the reconstruction project will include approximately 500 meters of the street, from Scott Street to Highway 60.

District officials said the project will modernize underground infrastructure and address local drainage issues. The scope of work includes replacing a 1960s-era watermain with a new PVC pipe, upgrading water service connections, resurfacing the road and restoring affected areas.

During the Jan. 26 council meeting, engineer Michael Parniak presented a report to council stating the project is linked to specific funding requirements and housing initiatives outlined in the District’s development plan.

“Unfortunately, the nature of the project is quite significant, and it could be a little bit of a burden to businesses, but the way it’s been designed and the staging of it, we’re all taking into consideration the impact it could have,” he said.

The report states the work will require lane restrictions, traffic detours, and extended construction durations, impacting businesses and traffic operations.

Parniak requested and received noise exemptions from council to accommodate the project’s construction schedule.

“The whole idea behind that is to get the contractor in and out as quickly as possible,” said Parniak.

Under the existing by-law, work is prohibited daily from 9:00 p.m. to 7:00 a.m., with further restrictions on Sundays that prevent activity between 7:00 a.m. and 12:00 p.m., as well as after 6:00 p.m.

Parniak said that while a contractor has not yet been selected, the project requirements will prioritize accessibility. He said the District is hoping to maintain continuous pedestrian access and ensure vehicular entry to driveways and businesses whenever possible.

The project is expected to be completed before 2027.

Mauricio Prado
Mauricio Pradohttps://www.mymuskokanow.com/
Mauricio Prado is a journalist seeking narratives beyond the surface to connect with people and community. A graduate of Fanshawe College's journalism program, Mauricio brings a keen eye for detail and a passion for storytelling to his work. His Salvadoran roots combined with his knowledge, allow him to bring a global perspective and sharp cultural understanding to his storytelling. If you have a story to share, email mprado@vistaradio.ca

Continue Reading

cfbk Now playing play

cfbg Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Scott Aitchison officially resigns his seat in the House of Commons

Scott Aitchison has officially resigned from his seat in the House of Commons following the Nov. 26 parliamentary sitting.

Planned hydro outage scheduled in Gravenhurst on Nov. 29

Hydro One has scheduled a planned power outage in Gravenhurst to carry out maintenance work on Nov. 29.

Town of Bracebridge to hold annual Holiday Market on Nov. 28

The Town of Bracebridge is hosting its annual Holiday Market on Nov. 28 at the Muskoka Lumber Community Centre.

Three Huntsville residents charged following drug trafficking investigation

Police say three Huntsville residents were arrested and charged with two counts of possession of a Schedule I substance for the purpose of trafficking and possession of proceeds of property obtained by crime.

Two Gravenhurst residents charged following theft at Bracebridge grocery store

Two Gravenhurst residents have been charged following a shoplifting incident at a grocery store on Muskoka Road 118 in Bracebridge.
- Advertisement -